4/9/2020 Timber Post Installation

5/2/2020 Roof Installation 1

5/9/2020 Roof Installation 2

6/14/2020 Roof Installation 3

7/10/2020 Gravel Poured and Plumbing Installation prior to Concrete

7/14/2020 Poured Concrete Installation
7/22/2020 Framing of the Walls
7/25/2020 Framing Completed
8/6/2020 OSB board and Wrap complete. Electrical started
8/18/2020 Sheet Metal Installed and Concrete Poured and Cut
10/2/2020 Insulation, Sheetrock Installable & Walls Painted
11/13/2020 Storage Room, Kitchen, Wood Ceiling
12/14/2020 Doors Installed, Storage Painted, Rough Grading